How Long Does It Take to Build an App? Realistic Timelines
11 January 2025 • LKM Software Ltd
How Long Does It Take to Build an App? Realistic Timelines
"How long will it take to build my app?" is one of the first questions we hear from clients. The honest answer is: it depends on many factors. This guide will help you understand realistic timelines and what affects them.
Quick Answer: App Development Timelines
| App Type | Typical Timeline | Example |
|----------|-----------------|---------|
| Simple MVP | 2-3 months | Basic booking app, simple directory |
| Standard App | 4-6 months | E-commerce app, customer portal |
| Complex App | 6-12 months | Multi-platform app with integrations |
| Enterprise App | 12-24+ months | Large-scale system with many features |
These are estimates for a competent development team working full-time on your project.
What Affects Development Time?
1. Scope and Features
The more features, the longer the timeline. Common features and their approximate impact:
| Feature | Time Impact |
|---------|-------------|
| User authentication | 1-2 weeks |
| User profiles | 1-2 weeks |
| Search functionality | 1-3 weeks |
| Payment processing | 2-4 weeks |
| Real-time chat | 3-6 weeks |
| Maps and location | 2-4 weeks |
| Push notifications | 1-2 weeks |
| Social media integration | 1-3 weeks |
| Admin dashboard | 3-6 weeks |
| Reporting and analytics | 2-6 weeks |
| AI/ML features | 4-12 weeks |
| Third-party integrations | 1-4 weeks each |
2. Platform Choice
Where will your app run?
- Web app only: Fastest to develop
- iOS only: Add 20-30% time vs web
- Android only: Add 20-30% time vs web
- iOS + Android native: Nearly double the work
- Cross-platform (React Native/Flutter): 30-40% more than single platform
3. Design Requirements
How polished does the user interface need to be?
- Basic/template design: Minimal impact
- Custom design: Add 4-8 weeks for UX/UI design
- Premium/branded design: Add 8-12 weeks
- Animations and micro-interactions: Add 2-4 weeks
4. Backend Complexity
What happens behind the scenes?
- Simple database operations: Included in base estimate
- Complex business logic: Add 20-50% time
- Real-time functionality: Add 30-50% time
- Heavy integrations: Add 2-4 weeks per integration
- Legacy system connections: Highly variable
5. Quality and Testing Requirements
How thoroughly must the app be tested?
- Basic testing: Included in estimates
- Comprehensive testing: Add 15-25% time
- Regulated industries: Add 25-50% for compliance testing
- Accessibility compliance: Add 10-20% time
Development Phases and Timelines
Phase 1: Discovery and Planning (2-4 weeks)
What happens:
- Requirements gathering
- User story mapping
- Technical architecture
- Project planning
- Initial estimates
Why it matters: Skipping this phase leads to rework later. Investing in planning can save 30-50% of total project time.
Phase 2: Design (3-8 weeks)
What happens:
- User research
- Wireframing
- Visual design
- Prototyping
- Design review and approval
Why it matters: Changes during design cost 10x less than changes during development.
Phase 3: Development (6-20+ weeks)
What happens:
- Backend development
- Frontend/app development
- API development
- Database setup
- Feature implementation
- Code review
This is the longest phase and scales with complexity.
Phase 4: Testing (2-6 weeks)
What happens:
- Unit testing (ongoing during development)
- Integration testing
- User acceptance testing
- Performance testing
- Security testing
- Bug fixing
Why it matters: Rushing testing leads to production issues that cost more to fix.
Phase 5: Deployment (1-2 weeks)
What happens:
- Production environment setup
- App store submissions (if applicable)
- Final data migration
- Launch preparation
- Go-live support
Phase 6: Post-Launch (Ongoing)
What happens:
- Bug fixes and patches
- Performance monitoring
- User feedback collection
- Feature enhancements
- Maintenance and updates
Real-World Timeline Examples
Example 1: Simple Booking App MVP
Scope: Web app for a local service business to accept bookings online.
Features: User registration, service selection, calendar booking, email confirmations, admin dashboard.
Timeline: 10-12 weeks
- Planning: 2 weeks
- Design: 2 weeks
- Development: 5-6 weeks
- Testing: 1-2 weeks
Example 2: Customer Portal
Scope: Mobile-responsive web app for customers to manage their account, view orders, and contact support.
Features: Authentication, account management, order history, document uploads, support tickets, notifications.
Timeline: 16-20 weeks
- Planning: 2 weeks
- Design: 4 weeks
- Development: 8-10 weeks
- Testing: 2-4 weeks
Example 3: E-commerce Mobile App
Scope: Native iOS and Android apps for an existing e-commerce business.
Features: Product browsing, search, cart, checkout, payment, order tracking, push notifications, reviews, wishlists.
Timeline: 24-32 weeks
- Planning: 3 weeks
- Design: 6 weeks
- Development: 12-18 weeks
- Testing: 3-5 weeks
Example 4: Enterprise Operations System
Scope: Comprehensive system for managing business operations with multiple user roles and integrations.
Features: Complex workflows, reporting, multiple integrations (ERP, CRM, accounting), mobile access, real-time updates, audit trails.
Timeline: 40-60+ weeks
- Planning: 4-6 weeks
- Design: 8-10 weeks
- Development: 24-36 weeks
- Testing: 4-8 weeks
How to Speed Up Development
1. Start with an MVP
Launch with core features only, then iterate based on real user feedback. You can often get to market in half the time.
2. Make Decisions Quickly
Every delayed decision adds to the timeline. Empower your team to make choices and avoid design-by-committee.
3. Use Proven Technologies
Cutting-edge tech has fewer resources and more unknowns. Mature technologies have solved problems you'll encounter.
4. Reduce Custom Design
Use design systems and component libraries. Custom design is expensive in both time and money.
5. Prioritise Ruthlessly
Not every feature needs to be in version 1. Focus on what delivers the most value to users.
6. Keep Scope Fixed
Scope creep is the biggest timeline killer. Lock requirements before development begins.
How to Get Accurate Estimates
Provide Clear Requirements
The more detail you provide, the more accurate the estimate:
- User stories or use cases
- Wireframes or mockups
- List of integrations needed
- Non-functional requirements (performance, security)
- Compliance requirements
Ask the Right Questions
When evaluating estimates:
- What's included and excluded?
- What assumptions are being made?
- What could cause the timeline to slip?
- How are changes handled?
- What's the testing approach?
Build in Buffer
Add 20-30% to any estimate for:
- Unexpected complexity
- Requirement changes
- Integration issues
- Testing and bug fixing
- Stakeholder review cycles
Our Approach to Project Timelines
At LKM Software Ltd, we provide realistic timelines based on experience delivering similar projects. We:
- Invest in discovery: Proper planning prevents problems
- Break work into sprints: Deliver value incrementally
- Communicate proactively: No surprises on timeline
- Manage scope carefully: Control changes to protect the timeline
- Test throughout: Find issues early when they're cheap to fix
Ready to Discuss Your Project?
Contact us for a free consultation. We'll discuss your requirements and provide a realistic timeline estimate for your specific project.
LKM Software Ltd
Software Development Experts
We are a professional software development company based in the West Midlands, specialising in custom web applications, mobile apps, AI integration, and API development. With over 15 years of combined experience, we help businesses across Birmingham, Wolverhampton, Telford, and Shrewsbury transform their operations through technology.
Published: 11 January 2025
Author: LKM Software Ltd
Topics: Software Development, Business